This spreadsheet was created to estimate the project cost and keep track of labor/labor estimates for FE-07. It is important we keep this up to date for future reference. Until now, the team has not been able to make accurate estimates on project lengths largely due to lack of experience. We are all students here. To remedy this, we keep track of our Labor estimates and actual time spent on projects to have a point of reference in the future.
The Financials are currently estimates. These will need to be updated as we start purchasing parts.
Keeping these up to date will aid in the Cost Report for Competition, budget request, and sponsorship opportunities.
Some unorganized information is available between the Google Drive and the R-Drive, that still needs to organized.